Detailed timeline
gantt
dateFormat YYYY-MM-DD
excludes weekends
axisFormat %Y-%m-%d
section FOLIO Community
2022.r1.0 (INN-Reach backend) :milestone, 2022-04-18, 0d
2022.r2.0 :milestone, 2022-08-08, 0d
2022.r3.0 :milestone, 2022-11-08, 0d
INN-Reach iii certification :milestone, 2022-11-22, 0d
INN-Reach GA :milestone, 2023-02-23, 0d
section Project Management
Refactor Timeline :done, 2022-02-21, 1w
Review Requirements :active, 2022-02-21, 38d
Documentation :active, 2022-04-01, 12w
Create Training :2022-05-01, 12w
Deliver Training :2022-09-01, 12w
section Data Migration
Inventory :active, 2022-03-01, 2022-05-31
Users : active, 2022-03-01, 2022-06-30
Acquisitions :active, 2022-03-01, 2022-08-31
Circulation: 2022-06-01, 2022-09-30
Dry Runs :2022-11-01, 2022-12-31
Law Data Mapping :d4, 2022-09-01 , 2022-12-31
Comprehensive Dry Runs :2023-01-01, 2023-04-30
section Operations
Scratch Environment :done, o1, 2022-03-01, 4w
Deploy Kiwi :active, crit, o2, after o1, 4w
Infrastructure improvements :o3, after o2, 4w
Deploy LDP :crit, o4, after o3, 4w
Deploy Lotus :o5, 2022-08-01, 4w
Deploy Morning Glory :o6, 2022-11-01, 4w
section Discovery
EDS over Sierra :active, d1, 2022-02-21, 12w
Relevancy Testing :12w
section Metadata - Deep Dives
Data Export: 2022-09-01,2022-09-30
Bound-withs: 2022-09-01,2022-10-15
Data Import: 2022-07-01,2022-09-01
Bulk Edit:
Deleting Records:
Local notes/Statistical codes:
Authority Control:
section Metadata - Data Import
Document active Sierra load profiles :active, 2022-02-28, 4w
Annotate Sierra load profiles :2022-04-01, 8w
Create basic profile :2022-09-01, 3w
Create and test necessary profiles :2022-10-01, 6w
Complete and Document Profiles :2022-12-01, 6w
section Metadata - Single Record
Copy Cataloging :active, 2022-03-15, 2w
Original Cataloging :active, 2022-03-15, 2w
Brief Bibs: 2022-04-01, 2w
Overlaying Bibs: 2022-04-01, 2w
Data Migration Timeline (detailed)
gantt
dateFormat YYYY-MM-DD
excludes weekends
axisFormat %Y-%m-%d
section Inventory
Mapping :active, 2022-03-01, 2022-05-31
Exemplar data loaded :active, 2022-03-01, 2022-03-30
100k Sample loaded :done, 2022-03-01, 2022-03-30
Approve Inventory Sample (Kiwi) :milestone, 2022-05-31, 0d
Full load - Inventory :crit, 2022-05-01, 2022-06-30
section Users
Mapping :active, 2022-03-01, 2022-05-31
Sample loaded :active, 2022-04-01, 2022-05-31
Approve User Sample :milestone, 2022-05-31, 0d
Full load - Users :2022-05-01, 2022-06-30
section Acquisitions
Mapping :active, 2022-03-01, 2022-07-31
Load Organizations :active, 2022-04-01, 2022-04-30
Load/Config Finance :2022-06-01, 2022-06-30
Orders (POs/POLs) Sample Loaded :2022-05-01, 2022-07-31
Approve PO Sample :milestone, 2022-07-31, 0d
Load all Orders :2022-07-01, 2022-08-31
Invoices:
section Circulation
Mapping :2022-06-01, 2022-08-31
Process Open Loans Sample :2022-07-01, 2022-07-31
Process Fees/Fines Sample :2022-08-01, 2022-08-31
Approve Loans Sample :milestone, 2022-08-31
Approve Fees/Fines Sample :milestone, 2022-09-31
Process all Loans :2022-09-01, 2022-09-30
Process all Fees/Fines :2022-09-01, 2022-09-30